6th Edition PMBOK® Guide—The Importance of Project Management


I am starting a project of going through the 6th Edition of the PMBOK® Guide and blogging about its contents.    The 6th Edition was released on September 22nd by the Project Management Institute, and the first chapter is a general introduction to the framework in which project management exists, starting with section 1.2 Foundation Elements (section 1.1 describes the purpose of the Guide).

In section 1.2.2, PMI discusses the importance of project management.

As you might suspect, the Project Management Institute does indeed think that project management is important to an organization.    There are three reasons:

  1.  It helps organizations execute projects effectively (getting the right things done)
  2.  It helps organizations execute projects efficiently (getting things done right)
  3.  It helps organizations achieve strategic objectives.

This last reason is important to emphasize, because there is a tendency to think of projects as simply on the level of tactics, i.e., the actual means of achieving an objective.  However, the project manager should consider himself or herself as a strategic ambassador, by learning from the sponsor what the strategic objectives of the organization are that the project will be tied to.   This is important in motivating team members who may not be aware of the larger impact their efforts on the project may have after the project has been completed.   But it also has a pragmatic component, because the project manager can take an active role in preventing changes that would jeopardize that strategic objective from being realized!

It is possible to overemphasize the importance of projects?   There are some in the agile community who feel that there is too much focus on projects and too little on products.   In the next post, I will discuss a post by Anthony Mersino in his review of the Agile Practice Guide on his blog Vitality Chicago which tries to put projects in the larger context of product development.

Advertisement

6th Edition PMBOK® Guide—Projects and Business Strategy Alignment


I am starting a project of going through the 6th Edition of the PMBOK® Guide and blogging about its contents.    The 6th Edition was released on September 22nd by the Project Management Institute, and the first chapter is a general introduction to the framework in which project management exists, starting with section 1.2 Foundation Elements (section 1.1 describes the purpose of the Guide).

In section 1.2.1, PMI introduces the definition of projects (discussed in the previous two posts) and it is then immediately followed by the relationship between project management and change management (this was covered in the previous post).   Then it goes on to show the relationship between project management and

  • business analysis (determination of the business value created by a project)
  • business strategy (the context in which a project is initiated by an organization)

When you ask the question of why a project is being created, there are two answers to the question.   One reason is because the entity requesting the project to be done wants to derive some business value or benefit from it.   The determination of what business value is created by a project is called the business analysis.    This was discussed in the previous post.

Business strategy

But the other reason is that project will align with the strategic objectives of the organization doing the project.

There are four general categories PMI gives for the context in which a project may be initiated:

  1. Meet regulatory, legal, or social requirements
  2. Satisfy stakeholder requests or needs
  3. Create, improve, or fix products, processes, or services
  4. Implement or change business or technological strategies

There are several examples of specific factors that correspond to these four categories listed in Table 1-1 on page 9 of the Guide.   Some of them, such as “legal requirements”, fit one category (“meet regulatory, legal, or social requirements”), while others, such as “market demand”, fit several categories (all of the categories above except the first one).

Because the business strategy of an organization is central to the reason for the project being created in the first place, it is important for the project manager to understand what that strategy is for a very pragmatic reason:   if conditions arise that prevent the project from aligning with the business strategy of an organization, or if that business strategy changes, then that project may be terminated by the sponsor!

The next section 1.2.2 of the Guide, discusses the importance of project management from the standpoint of effectiveness and efficiency.   That is the subject of the next post.

6th Edition PMBOK® Guide—Projects and Business Value Creation


I am starting a project of going through the 6th Edition of the PMBOK® Guide and blogging about its contents.    The 6th Edition was released on September 22nd by the Project Management Institute, and the first chapter is a general introduction to the framework in which project management exists, starting with section 1.2 Foundation Elements (section 1.1 describes the purpose of the Guide).

In section 1.2.1, PMI introduces the definition of projects (discussed in the previous two posts) and it is then immediately followed by the relationship between project management and change management (this was covered in the previous post).   Then it goes on to show the relationship between project management and business analysis, which determines the business value that the project is designed to create.

This relationship between project management and business analysis is made explicit in PMI’s new publication “Business Analysis for Practitioners:  A Practice Guide.”   But for the purpose of this introductory section on project management, PMI defines business value as

“the benefit that the results of a specific project provides to its stakeholders”

and it can take the following forms:

“the return, in the form of time, money, goods or intangibles in return for something exchanged.”

Here are some important points to consider regarding this statement.

  1.  When people think of “business value”, they might think of money, which is normally thought of when you hear the phrase “bottom line”.   But there are intangible benefits that a company could create a project for, such as brand recognition, reputation, or even goodwill.
  2. The description of business value as a benefit for stakeholders is reflected in the name for one of the two project business documents that are inputs to the creation of the project charter:  the “project benefits management plan.”   The “project business case” shows how the project will create business value for the stakeholders, but the “project benefits management plan” shows how this business value, once created, will be maximized and sustained over time.

Because the creation of business value is central to the reason for the project being created in the first place, it is important for the project manager to understand what that value is for a very pragmatic reason:   if conditions arise that prevent the project from creating business value for the stakeholders, then that project may be terminated by the sponsor!

When you ask the question of why a project is being created, there are two answers to the question.    One reason is because the entity requesting the project to be done wants to derive some business value or benefit from it.    But the other reason is that project will align with the strategic objectives of the entity doing the project.   That topic is the subject of the next section in the Guide and will be discussed in the next post.

6th Edition PMBOK® Guide—The Relationship between Project Management and Change Management


I am starting a project of going through the 6th Edition of the PMBOK® Guide and blogging about its contents.    The 6th Edition was released on September 22nd by the Project Management Institute, and the first chapter is a general introduction to the framework in which project management exists, starting with section 1.2 Foundation Elements (section 1.1 describes the purpose of the Guide).

In section 1.2.1, PMI introduces the definition of projects (discussed in the previous two posts) and it is then immediately followed by this bold statement:

“Projects drive change”

This is a declaration that a project manager is, almost by the very nature of what he or she is doing, also a change agent!

The reason why this statement leaped out of the page for me was that I had just been just recently discussing the subject with Elizabeth Allen, a project manager in the PMO at Nemours Children’s Health System for 12 years who has been leading change efforts for +25 years.  She is preparing a presentation for the PMI Global Conference to be held in Chicago in late October 2017 (next month).    The title of her talk is “Becoming a Holistic Agent of Change.”  In it she describes some of the theoretical models of how organizations process change, but she also recounts some of the personal experiences she had on a recent project involving change of a hospital system.   The statement she made that struck me was that every project manager is automatically a change agent, and managing the resistance to change is part of what makes a project manager effective in his or her job.

Although what she said I thought was intuitively true, I didn’t realize that PMI would be stating it at the very beginning of the new PMBOK® Guide!   In the section describing the relationship between project and change management, PMI announced that it has published its own guide to change management called “Managing Change in Organizations:  A Practice Guide.”   In terms of knowledge areas in the PMBOK® Guide, the biggest impact a greater understanding of change management would have for a project manager is probably in the area of Stakeholder Management (Chapter 13).  This is because many stakeholders within the organization will be the source of resistance to a project for the simple reason that is does represent change to that organization.   This is probably more true for internal projects whose objectives are to change the business processes of the organization rather than external projects that are done for customers.

So in this section, PMI makes explicit the relationship between project management and change management, and it puts “skin in the game” by announcing its own change management guide.    It also put the fire of ambition into me, as I now want to study change management after I finish studying for and passing the Project Management Professional exam!

 

6th Edition PMBOK® Guide—Chapter 1 (Introduction): What is a Project? (2)


 

I am starting a project of going through the 6th Edition of the PMBOK® Guide which was released last week by the Project Management Institute and blogging about the contents.   The first chapter is a general introduction to the framework in which project management exists, starting with section 1.2 Foundation Elements (section 1.1 describes the purpose of the Guide).    This section starts with the definition of a project, a good place as any to start:

“A project is a temporary endeavor undertaken to create a unique product, service, or result.”

As I mentioned in yesterday’s post, the key words in this definition are “temporary” and “unique.”   I discussed the “unique” aspect of projects in yesterday’s post; I wanted to focus on the other key word today and that is “temporary.”   In an organization, a project stands in contrast to its regular operations, which if not permanent, are at least continuous (ongoing) or continual (happening repeatedly at regular intervals).

But the PMBOK® Guide, in discussing on page 6 the fact that a project is a temporary endeavor, mentions another important aspect of a project.   When exactly does it end?    Well, since the definition of a project is an endeavor to create a unique product, service, or result, it makes sense that a project ends when its objectives have been achieved.

But a project can also end when the objectives will not or cannot be achieved for the following reasons:

  • funding for the project is exhausted, or the human and/or physical resources are no longer available
  • the business need for the project no longer exists
  • legal cause or regulatory change

All of these reasons are discussed in an upcoming section on why a project is initiated in the first place.   When those reasons go away, so can the project!

Besides being a general point that is important to understand, knowing that a project can be terminated when it can no longer achieve its objective will help you when you study for the Project Management Professional (PMP).

Here are some examples of questions that illustrate the point described above.

Question:   You are the project manager on a project and your sponsor gives you the news that upper management is terminating your project because it can no longer serve the business need for which it was started in the first place.    What process are you now in?

Answer:   Close Project or Phase (process 4.7).

When the project is terminated by the sponsor, all work on the project itself will cease, but you as a project manager will still have to complete the final process, which is Close Project or Phase.    Although the product, service or result of the project will not be realized, that doesn’t mean that the project was a total “waste of time.”   However, it will be unless you do this process.   The people working on your project team will be released to pursue new projects, but before they go, it is important for you and your team to document the knowledge gained by you and your team while you were doing the project by creating a final register of the lessons learned so that other projects may benefit from your efforts.   That knowledge will help other project managers in getting their projects to the finish line!

Here’s a more technical question involving earned value measurement, but related to the same topic.

Question:    during the Close Project or Phase process, what will the SPI be?

A) greater than one

B) equal to one

C) less than one

D) all of the above are possible

Answer:  the correct answer is d).   In order to understand this, let’s review what the SPI is.   It stands for the Schedule Performance Index, and is taken to be the cumulative Earned Value or EV (the value of the actual work done on the project) divided by the Planned Value or PV (the value of the work that was planned to be done on the project).

If your project has achieved the objectives, then the actual work done (EV) should equal what was planned to be done (PV), and therefore EV/PV = 1.0.   However, if your project was terminated because the project was not able to achieve the project objectives, then the actual work done (EV) will be LESS than what was planned to be done (PV), in which case EV/PV < 1.

Can the SPI be greater than one at the end of a project?    If SPI is greater than one at the end of a project, then that implies that the actual work done (EV) is GREATER than what was planned to be done, which means that in order to achieve the objectives, you had to do more work than you had planned on doing.   So it is possible, although obviously not an ideal situation.

As a side note, you can end up having more project scope than you planned for, as in this scenario when you had to do more work than you planned to get to the finish line, but about the product scope?   Can you have more product scope than you planned for, i.e., more features and requirements in your final product than were called for in your original requirement?   The answer to this according to PMI is a resounding “NO!”, because this would be doing something called “gold plating,” which is giving the customer something that he or she did NOT ask for, and may not be something that the customer even wants.

So in conclusion, a project is a temporary endeavor, which means it will end, but it can end either because it does or does not meet its objectives.   The next post introduces a very important concept about projects, which is that they drive change.   So any project manager therefore is automatically a change agent!

 

 

 

 

6th Edition PMBOK® Guide—Chapter 1 (Introduction): What is a Project?


Today I am starting a project of going through the 6th Edition of the PMBOK® Guide which was released last week by the Project Management Institute and blogging about the contents.    I blogged about the contents of the 4th Edition in order to prepare for the Certified Associated in Project Management (CAPM) certification exam; I blogged about the contents of the 5th Edition in order to lead a study group of PMI members who were studying for the Project Management Professional (PMP) certification exam, and now I am blogging about the 6th Edition to take the exam myself when it becomes available in the first quarter of 2018.

The first chapter is a general introduction to the framework in which project management exists, starting with section 1.2 Foundation Elements (section 1.1 describes the purpose of the Guide).    My first question on cracking open the new 6th Edition was “has the definition of a project changed?”   The answer is no; it is as follows

“A project is a temporary endeavor undertaken to create a unique product, service, or result.”

The key words here, I believe, are “temporary” and “unique.”  What you should be doing in thinking of this definition is not just what a project is, but what it is not:   it contrasts with the regular operations of a business or organization which are activities that are “ongoing” and often “repetitive.”   Also important is the fact that the project is done for a specific purpose, although that purpose may be tangible (a product), intangible (a result), or something in between (a service).

Let’s think about an example to clarify one’s understanding of the definition, one that I take from my professional experience.

Scenario A–The Reserve Project

Company A is an insurance company which is required by insurance regulations to calculate the reserves it is holding for its insurance claims.   The reserves represent the amount of money set aside for the insurance company to meet future payments associated with claims incurred but not yet settled.    The reserves have to be calculated by the ending of each fiscal year, and so three months before that date, Company A initiates the “Reserve Project,” which has as its goal the calculation of the reserves to be reported to the insurance regulatory agencies.    To achieve this result, a project manager is chosen to lead the claims adjusters, who act as the project team members carrying out the project.    A budget and a schedule are created, usually copied from the previous year when the same project was done last time.

Question:   Is this a project according to PMI’s definition?

Answer:    Although the company calls it a project, it is really more along the lines of a business operation.    Yes, it may have some surface singularities to a project, in that it is done for a specific purpose, a manager is assigned to manage the activities, there is a schedule and budget, etc., but the key words in the scenario are “the same project was done last time.”   It is not a unique result, but the same result that has to be done in the same way at the same time every year.    It is an operational activity, albeit one that is done not continuously throughout the year, but continually (i.e., done at regular intervals at a specific time of the year).

Scenario B–A Six Sigma Project

Company B creates a unique product, but then discovers that there is a defect in the product.    They decide to do what is called a “Six Sigma project” which will go and correct this defect.

Question:  Is this a project according to PMI’s definition?

Answer:   Although the answer might not be clear in the basic definition, in the explanatory paragraphs below the definition, PMI goes into more detail and says that a “unique product” can be any of the following:

  • a component of another item
  • an enhancement or correction to an item, or
  • a new end item in itself (e.g. the correction of a defect in an end item).

A Six-Sigma project would definitely fall into the last of these definitions, since it is correcting a defect in an end item which had been created in a previous project.

This post covers the portion of the definition which contains the word “unique”; the next post will cover the portion of the definition which contains the word “temporary.”   Additional posts in this series will cover the relationship between project management and change management, the creation of business value, and the factors which cause organizations to initiate projects in the first place.

 

 

 

 

The new 6th Edition PMBOK® Guide and the future of Project Management


On Friday, September 22nd, I received my copy of the 6th Edition of the Guide to the Project Management Body of Knowledge (or PMBOK® Guide for short).

I did a brief review of the individual changes from the 5th to the 6th edition with yesterday’s post on September 23rd.   Before I start going through the new PMBOK® Guide from cover to cover, I wanted to say that my first macro-impression was that this new Guide truly represents not just the current state-of-the-art of project management, but also of future of project management as well.

This is because, as I mentioned in yesterday’s post, not only does the new PMBOK® Guide come with an Agile Practice Guide companion, but each knowledge area comes with a section that explain how to adapt the contents to an agile project management environment.    This is why I feel it represents the future of project management, which is not a mindset that thinks of “agile vs. traditional” methodologies, but a hybrid “agile + traditional” mindset.  I have watched several presentations by thought leaders describing what project management will look like 10 to 15 years from now, and they concur with this prediction.

The other positive development I see in an institutional one, because the Agile Practice Guide that accompanies the PMBOK® Guide is written by the Project Management Institute (PMI) in collaboration with the Agile Alliance®.   There is a tendency with institutions like PMI that are setting standards to want to build their “brand” as being the authoritative one, and this goal, understandable as it is, could have led PMI to decrease, rather than increase, their cooperation with those other institutions.    I’m relieved to see evidence of this cooperation because in my opinion that focuses on the needs of the members.   Many of those members are going to be either members of other standard-setting groups and/or alliances or they are going to interact with those members, and the Agile Practice Guide will encourage those interactions.

What does this mean for MY particular future?    I got the Certified Associate in Project Management (CAPM) back in October 2012, and this certification has a five-year lifespan.    In the meanwhile, I have been volunteering on projects for my local PMI chapter here in Chicago and more recently with PMI Global in preparation for their Project Management Global conference that will take place next month (October) in Chicago.   I have been using this volunteer experience towards the experience requirement for getting the top-level certification, the Project Management Professional or PMP certification.

But as October 2017 came closer and closer this year, I heard the rumor that the new 6th Edition PMBOK® Guide had a lot more content related to agile methodologies and I decided that rather than taking the PMP based on the 5th Edition, I would wait until the 6th Edition came out in late September so that when I passed the test, I could tell prospective employers that my PMP certification was “state-of-the-art” because it was based on the latest edition of that PMBOK® Guide.

However, there is still no certain date of when you can go and take the PMP exam based on the new 6th Edition of the PMBOK® Guide, although rumors have it that it will sometime in the first quarter of 2018.    So I decided to do the following:

  • Retake the CAPM exam now, so that in case my first attempt at taking the PMP doesn’t work out, I’ll still have a project management certification to fall back on.  (This is basic risk management…)
  • Blog on the contents of the 6th Edition, not only to understand them for myself but also to help those in my local PMI chapter and elsewhere who aim like to me to take the PMP exam based on the new material.
  • Wait until PMI announces an official date for the exam.   If it’s in the first quarter of 2018, then three to six months time would be enough to cover the contents of the new 6th Edition in my blog, and then to look to one of the exam prep companies (Velociteach, RMC, etc.) to see when they come out with their preparation materials.

If PMI decides to put out the PMP certification exam material in the second quarter or later, then I may have to rethink this strategy, perhaps by going ahead with the PMP exam based on the 5th Edition material which I know backwards and forwards (not just because of my blog, but because I ran a PMP exam study group for my local PMI chapter when I was the Director of Certification there).    I would in that case have the certification but still be able to tell prospective employers that I’m aware of the new 6th Edition contents as well because of my work in the next few months to blog about them.

So as you can see, the new 6th Edition of the PMBOK® Guide has helped me map out my future in my deepening relationship with the world of project management, and I hope that you can use it to do the same!

A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—New Sixth Edition just published!


On September 22nd, the Project Management Institute (PMI) published their newest 6th Edition of their Guide to the Project Management Body of Knowledge (or PMBOK® Guide for short).

I received it yesterday and have been looking it over to compare it with the previous 5th Edition of the PMBOK® Guide which was published in January 2013.    It has been therefore almost five years since the last edition, and I wanted to outline the main changes I have seen between the old 5th Edition and the current 6th Edition.

1. Agile Methodologies

The biggest change in the 6th edition is that it not only comes with a companion volume called the Agile Practice Guide, which was a collaborative effort by PMI and the Agile Alliance, but that each knowledge area of the 6th Edition of the PMBOK® Guide comes with a section on applying that knowledge area in an agile work environment!

This reflects a huge sea-change from the 5th Edition, where agile methodologies were noted almost in passing in the general sections on project life cycle, but not discussed elsewhere in the Guide.   Now they are woven into the very fabric of the Guide itself, which reflects the reality that the future of project management is not in an “agile vs. traditional” framework, but rather an “agile AND traditional” framework.

Here are some additional changes I noted.

2.  ANSI standard

A lot of the foundational elements of project management that were included in chapters 1-3 of the old edition have been moved into the second part of the 6th edition PMBOK® Guide in a section called the ANSI Standard for Project Management.   Information on the different project life cycles, for example, is now in this second part.    This contains a lot of reference material that project managers will need to be aware of in order to get full use out of the information contained in the Guide.

3.  Process Groups and Knowledge Areas

Well, the good news is that the 5 process groups and 10 knowledge areas that were in the 5th Edition have not changed–they are still the same in the 6th Edition.    There is only one change in the title of a knowledge area–Project Human Resources Management has become Project Resources Management (see paragraph 5 below).

4.  New Processes

There are 49 processes in the 6th Edition, as opposed to 47 in the 5th Edition.   This is a net increase of 3 processes, which comes about by the elimination of one process

  • Close Procurements, which has now been folded into Control Procurements

and the creation of 3 new processes:

  • 4.4 Manage Project Knowledge–this new process in the Integration Management knowledge area moves the creation of Lessons Learned from the Close Project process done once at the end of the project to the creation of a Lessons Learned register which is created and updated throughout the project during the Executing Process Group.   This can be seen as an influence from the world of agile project management methodology.    For example, one of the key questions asked in a Sprint Retrospective, a process set up by the Scrum Alliance in its agile methodology, is “what could we do differently to improve?”   The benefits of continuous improvement during a project are now harnessed rather than simply being applied from project to project.
  • 11.6 Implement Risk Responses–this is an additional process in the Risk Management knowledge area done in the Executing Process Group.   It implements the risk responses that were planned earlier in 11.5 Plan Risk Responses.
  • 9.6 Control Resources–I was just listening to a CD that came with Andy Crowe’s book The PMP® Exam–How To Pass On Your First Try, and one of the commentators on the CD said there was no “Monitoring and Controlling” process for the Human Resource Management knowledge area–but that there should be!   Well, he now has his wish because there IS such a process in the 6th Edition, called “Control Resources”.

5.  Human Resources → Resources

Called me old-fashioned, but I’ve seen the change from “staff” to “personnel” to “human resources” to “resources.”  Don’t let the terminology change fool you, though, because the newly titled “Project Resource Management” is still dealing with people!   In fact, I think this knowledge area has the largest increase in the number of processes.   There are two new processes, the first one 9.2 Estimate Activity Resources moved from Project Schedule Management to Project Resource Management in the Planning process group, and the second one described above (9.6 Control Resources) in the Monitoring and Controlling process group.

I plan to start blogging again to describe the contents of the 6th Edition, section by section, until I cover the entire PMBOK® Guide, the ANSI Standard, and the new Agile Practice Guide.  However, the one question I am dying to find the answer to is:   now that the 6th Edition is published, when will the actual PMP® exam be available from PMI?